S. M. A. Zomorodian, H. Chochi. Numerical Analysis of Earth – Rockfill Dams Behavior, During Construction and First Stage Impounding (Case Study: Masjed-e-Soleyman Dam). jwss 2013; 16 (62) :229-242
URL: http://jstnar.iut.ac.ir/article-1-2507-en.html
, mzomorod@shirazu.ac.ir
Abstract:   (13183 Views)
Excess pore water pressure in clay core dams during construction and primary filling reservoir (first impounding) causes initiation and progression of hydraulic fracture. In this research, the instrumentation data during construction and first filling reservoir (first impounding) was analyzed. It measured internal deformations, pore water pressures and total vertical stresses and compared with the analysis results in Masjed-e-Soleiman dam. To do this analysis, GEOSTUDIO 2004 V. 6.02 software was used. The staged construction of the dam was the model in the form of 2D coupled consolidation. The Non-linear elastic model for the core material and Linear Elastic model for other zones were incorporated into the models. For exact assessment and to obtain correct parameters of the constitutive model, the triaxial tests were performed on the core material of Masjed-e-Soleiman Dam and acceptable results were obtained.
Full-Text [PDF 576 kb]   (8679 Downloads)    
Type of Study: Research | Subject: Ggeneral
Received: 2013/03/13 | Published: 2013/03/15

Add your comments about this article : Your username or Email:
CAPTCHA

Rights and permissions
Creative Commons License This work is licensed under a Creative Commons Attribution-NonCommercial 4.0 International License.

© 2024 CC BY-NC 4.0 | JWSS - Isfahan University of Technology

Designed & Developed by : Yektaweb